Fluxys pulls a 1.4 km hydrogen pipeline under Sint-Gillis-Waas in a single stretch

On 19 November 2026, in Sint-Gillis-Waas, a 1.4-kilometre hydrogen pipe was pulled into the ground in a single stretch. The steel pipe had first been welded together on site, then drawn through a borehole prepared under roads, a cycle highway and part of the Stropersbos woodland, at a pace of around 200 metres an hour.
The operation sits on the Zelzate-Kallo hydrogen pipeline, which will connect the industrial clusters around the ports of Ghent and Antwerp. The route is an important link in the further development of a hydrogen network in Belgium, within the federal hydrogen strategy and the Flemish hydrogen vision. Completion of Zelzate-Kallo is still expected in spring 2027.
A borehole instead of a trench
The crossing was designed to avoid closing the F411 cycle highway, Kluizendijkstraat and Zalegemdijk for weeks. The first proposal was to dig a trench, which would have cut the roads towards De Klinge and Meerdonk, and the cycle path, for a long time and forced large diversions. A different method was therefore chosen.
The contractor first drilled a long borehole under a section of the Stropersbos and the roads, while the 1.4-kilometre pipe was welded together above ground. On 19 November the string was pulled through as one piece. Over Kluizendijkstraat, a temporary structure of containers and pulley systems carried the pipe above the road before it disappeared into the ground. Each 18-metre section weighs 4 tonnes.
The pipeline runs to the north of the E34, in a conduit lane. The same three crossings - the F411, Kluizendijkstraat and Zalegemdijk - were to be bored under rather than broken open, a point already agreed with the municipality of Sint-Gillis-Waas.
The Zelzate-Kallo pipeline
The Zelzate-Kallo hydrogen pipeline is about 36 kilometres long and 600 millimetres in diameter, and crosses Zelzate, Wachtebeke, Moerbeke-Waas, Stekene, Sint-Gillis-Waas and Beveren. Construction started in spring 2025, was interrupted after an appeal against the environmental permit, and resumed on 12 January 2026.
The Flemish government gave final approval to the conduit lane on 7 June 2024. A declaration of public utility followed by royal decree on 15 December 2024. The environmental permit for the route was granted by ministerial decree on 31 January 2025; after the appeal and an agreement with the parties concerned, the permit is again in force. A hydrogen transmission permit was granted by ministerial decree on 6 March 2025. Fluxys has since applied to update the environmental permit for dewatering during the works, without changing the route or the pipeline itself. A public consultation on that update opened on 12 November 2026.
A section of Belgium's hydrogen network
The subsidiary Fluxys hydrogen began building its hydrogen pipeline network in early 2025. In April 2024 it was appointed as the operator of an open-access hydrogen transport network in Belgium. The pipelines are laid with multi-purpose technology so they can also carry other molecules if necessary.
A 14-kilometre pipeline network in the port of Antwerp has recently been completed from a technical perspective and is available to the market. The Zelzate-Kallo section is under construction and is expected to be completed in spring 2027. These pipelines are a strategic link in the federal and Flemish hydrogen strategies, for energy supply and the decarbonisation of industry in Belgium and neighbouring countries.
Skills on a live crossing
The Sint-Gillis-Waas operation illustrates the skills required to take a hydrogen pipeline under roads and a cycle highway without opening a long trench: directional drilling, on-site welding of a continuous string, lifting and alignment, and a controlled pull through a prepared borehole. These are the disciplines of pipeline construction, geotechnics and lifting operations, applied to a live corridor next to the E34.
The 19 November pull is a visible step on the route between the two port clusters. It does not, on its own, complete the Zelzate-Kallo pipeline, whose completion is still expected in spring 2027.
Looking for Engineering & IT opportunities in permanent and freelance roles in Belgium? Browse the latest jobs on Engineering.jobs.
Olivier Lambert | Engineering.jobs
Are you a recruiter or employer? Publish your latest company news and job offers on Engineering.jobs to increase your company's visibility, strengthen your employer brand and attract future employees. Use our specialised engineering and IT CV database to find candidates who match your needs. Contact us today to find out more about our solutions.